Case study · Third-party logistics (3PL) · multi-site fulfilment · Commissioned 2025

Tier-1 UK 3PL operator · 2MWp solar across 4 distribution centres

2.0 MWp combined across 4 distribution centres commercial solar PV installation with combined grant + tax relief stack delivering N/A (PPA — immediate positive cashflow) post-tax payback on £1,400,000 gross capex.

Last reviewed 12 May 2026 2 min read By Case studies

Anonymised composite case study

Names, dates and exact financial figures have been changed to preserve client confidentiality. Project structure, funding combinations, technical configuration, and order-of-magnitude figures are real and based on completed work. Full editorial disclosure on the about page.

Project snapshot

SectorThird-party logistics (3PL) · multi-site fulfilment
LocationEast Midlands + South East + North West
System size2.0 MWp combined across 4 distribution centres
Battery storageNone on solar; standby diesel maintained
Gross project capex£1,400,000
Grant value£0 (PPA structure — 0% capex from operator)
Year-1 tax reliefN/A (PPA — operator buys electricity, not asset)
Net effective cost£0 capex; £74,000 net annual saving vs grid (year 1)
Annual savings/revenue£128,000 grid avoided - £54,000 PPA payments = £74,000
Post-tax paybackN/A (PPA — immediate positive cashflow)
CO2 saving168 tCO2e/year
Year commissioned2025
Gross capex£1,400,000
Less grant£0 (PPA structure — 0% capex from operator)
Less tax reliefN/A (PPA — operator buys electricity, not asset)
Net cost£0 capex; £74,000 net annual saving vs grid (year 1)

Context

The 3PL operator runs UK fulfilment services for major retail and ecommerce brands — Tesco direct, Amazon overflow, John Lewis, Boots, and several premium beauty and apparel brands. Annual revenue £180m, 920 staff across 4 main distribution centres plus 2 smaller fulfilment hubs.

In Q3 2024, the operator's three largest customers (collectively 70% of revenue) tightened supplier sustainability requirements simultaneously — each requiring Scope 1+2 disclosure plus a 30% reduction pathway by 2030. The operator needed credible Scope 2 reduction across its 4 main sites without consuming capex needed for ongoing automation and labour productivity investment.

The challenge

Three constraints shaped the approach:

1. **Capex preservation.** The 3PL was deep into a £40m automation programme (AS/RS systems, conveyors, robotic picking). Solar capex would compete directly with automation capex — not acceptable to the board.

2. **Multi-site complexity.** 4 main DCs in different DNO regions (UKPN, Northern Powergrid, WPD, ENW). Different DNO connection processes, different export limits, different timelines.

3. **Tenant arrangement.** All 4 DCs were leased from REIT landlords. Solar required landlord consent and lease variation.

4. **Time pressure.** Customer audits started Q3 2025 — 12 months to install and demonstrate operating reductions.

Funding approach

The team structured a behind-the-meter PPA across all 4 sites with a specialist solar finance investor:

1. **Investor builds and owns solar.** Investor's specialist developer constructs 2MWp combined across the 4 sites. £1.4m capex deployed by investor.

2. **3PL takes the electricity.** Operator agrees to take 100% of generation at fixed rate of 8p/kWh for 25 years (escalated 2% annually, capped at 3%).

3. **Landlord lease variation.** REITs agreed to lease variation in exchange for £0 cost — sustainability disclosure helps their own ESG reporting.

4. **Customer disclosure ready.** PPA structure produces verifiable Scope 2 reduction data exportable to customers' supplier scorecards.

Funding structure:

- **Investor capex:** £1.4 million (fully funded by specialist solar fund) - **Operator upfront cost:** £0 - **Annual PPA cost:** £54,000 (at 8p/kWh × 670,000 kWh self-consumption combined) - **Avoided grid import:** £128,000 (at 19p/kWh blended commercial rate × 670,000 kWh) - **Net annual saving:** £74,000 from year 1

Outcome & performance

All 4 sites commissioned by Q4 2025. Year-one combined performance:

- **Combined solar generation:** 1,900,000 kWh across 4 sites - **Combined self-consumption:** 35% (670,000 kWh) - **Combined export (taken by investor):** 1,230,000 kWh - **Annual avoided import cost (operator):** £128,000 - **Annual PPA payment (operator → investor):** £54,000 - **Operator net annual saving:** £74,000 from year 1 - **Operator CO2 reduction reporting:** 168 tCO2e/year - **All 3 major customer audits passed Q3 2025-Q1 2026.** Contracts retained.

The operator preserved all capex for the automation programme while delivering Scope 2 reduction. The investor earned utility-scale returns across a portfolio of long-tenure logistics tenants. Win-win structure now being replicated across the 3PL's smaller fulfilment hubs.

Lessons learned

  • PPA structures are highly effective for capex-constrained operators. £0 upfront, immediate positive cashflow, demonstrable Scope 2 reduction.
  • Multi-site programmes achieve materially better unit pricing than single-site projects — typically 15-25% cheaper £/Wp at portfolio scale.
  • REIT landlords are increasingly motivated to support solar — improves their own ESG reporting and Reduces lease default risk.
  • Customer audit timelines (typically 12 months from supplier code update to first audit) drive procurement urgency more than government policy.
Donovan Fawcett · Director, SEO Dons Ltd Twelve years in UK commercial solar SEO and grant advisory. Editorial policy & independence.

Could a similar approach work for your business?

Free 60-second eligibility check tells you exactly which grants, tax reliefs and finance routes apply to your specific business.

Free eligibility check Read more case studies
Call Eligibility check